Project Brief:
The purpose of the proposed Hawiyah Unayzah Gas Reservoir Storage Pro¡ect is to provide the necessary facilities to store off-peak surplus sales gas via in¡ection into the Hawiyah Unayzah reservoir during the low-demand season for reproduction back into the Master Gas System (MGS) during high demand; thereby maximizing the gas plants' utilization.
First of its kind gas storage pro¡ect for Saudi Aramco, it includes a design compression facility for in¡ecting 1500 million standard cubic feet per day (MMSCFD) and a design reproduction facility for reproducing 2000 MMSCFD of gas during peak consumption to produce sales quality gas.
The project will enable Aramco to in¡ect 1.5 bscfd of surplus natural gas from the MGS into the Hawiyah Unayzah Reservoir by 2022. In addition, the processing facilities will be able to reproduce up to 2.0 bscfd of gas stored for reintroduction into the MGS by 2024.
Scope Of Work:
Diar Consulting Group shall generate the As-built Drawings from redline drawings in accordance with Saudi Aramco MicroStation Draft-ing Procedures and iPlant Uploading Process.